Project Updates

Project Update 5/7/2021

07 May 2021

/

Staff

Work completed this week: SE 4th Ave between SE 2nd St to SE 3rd St – grading rock base is completed and primed and ready for ...

0
0

Project Update 5/6/2021

06 May 2021

/

Staff

Crews continue pouring concrete sidewalks & driveways along SE 3rd St between SE 2nd Ave to SE 3rd Ave and also along SE ...

0
0

Project Update 5/5/2021

05 May 2021

/

Staff

Crews continued pouring new sidewalks & driveways along NE 3rd Ave between NE 2nd St to NE 3rd St. On SE 4th Ave from SE ...

0
0