Work completed this week

  • Gravity Sewer Replacement in Alleyway 6 in now complete.
  • Alleyway 6 South Section – Stone Base complete and Concrete Header Curbs installed.
  • Alleyway 6 North Section – Excavation for Subgrade nearing completion.
  • SE 4th Ave between SE 8th St to SE 7th St – Pavement Area for new drainage work pulverized.
  • SE 4th Ave between SE 8th St to SE 10th St – Crews Continued with Clearing and Grubbing ahead of Roadway Improvements.

Work scheduled for Week of October 19th thru October 23rd

  • Alleyway 6 South Section – Pervious Concrete installation to begin.
  • Alleyway 6 North Section – Crews to begin placing the 6” Stone Base.
  • SE 4th Ave between SE 8th St to SE 7th St – Installation of new drainage pipes and structures to begin.
  • SE 4th Ave between SE 8th St to SE 10th St – Installation of new sidewalks and driveways to begin.

Daily Street Closures/Detours

  • Closures along SE 4th Ave with occur in Work Zone Areas. Please follow posted detours and watch for Flaggers in Work Zone Areas.