Project Update 3/26/2021

Work completed this week:

  • SE 2nd Ave between SE 3rd St to SE 4th St – Pavement reconstruction continued with excavating and installing new 8” Rock Base.
  • Alleyway 3 & 6 – Installation of Traffic Bollards.

Work scheduled for week of March 29th:

  • SE 4th Ave at SE 5th St Intersection – Work is scheduled to begin Monday 3/29/21 on the sewer repair at the intersection.
  • SE 2nd Ave between SE 3rd St to SE 4th St – Continue Pavement Reconstruction, Concrete Curbs, Sidewalks & Driveways.
  • Alleyway 3 & 6 – Complete Traffic Bollard installation for protection of the Utility Poles.

Daily Street Closures/Detours

  • Closures along SE 4th Ave and SE 2nd Ave. will occur in Work Zone Areas.
  • Please follow posted detours and watch for flaggers in Work Areas.