Project Update 4/14/2021

The contractors continue with roadway reconstruction on SE 4th Avenue between SE 3rd and 4th Streets and sidewalks and driveways on SE 2nd Street between 3rd and 4th Avenues.
The contractor also continues working in the alleyways setting up for the sewer lining of SE 4th Avenue from SE 10th Street north to SE 6th Street.