Project Update 4/16/2021

Work completed this week:

  • SE 4th Ave between SE 2nd St to SE 4th St – crews continued with installing new concrete sidewalks, driveways and curbs and also installing the new 8” Rock Base and grading between SE 3rd St to SE 4th St.
  • SE 2nd St between SE 3rd Ave to SE 4th Ave – crews excavated and installed new concrete curb & gutter for the new parking areas along the north side of SE 2nd St.
  • SE 4th Ave between SE 5th St to SE 6th St – crews finished installing the drainage exfiltration trench.

Work scheduled for week of April 19th:

  • SE 4th Ave between SE 2nd St to SE 4th St – continue excavation for stabilized subgrade and installing the new rock base at the intersection of SE 4th Ave and SE 3rd St.
  • SE 2nd St between SE 3rd Ave to SE 4th Ave – continue Pavement Reconstruction including new concrete curb & gutters, sidewalks and on-street parking areas.
  • SE 3rd Ave between SE 2nd St to SE 3rd St – begin installing new concrete sidewalks & driveways.
  • SE 4th Ave from SE 5th St to 10 St. – 30” sewer main lining

Daily Street Closures/Detours

  • Closures along SE 4th Ave will occur in Work Zone Areas.
  • Please follow posted detours and watch for flaggers in Work Areas.