Project Update 5/5/2021

Crews continued pouring new sidewalks & driveways along NE 3rd Ave between NE 2nd St to NE 3rd St. On SE 4th Ave from SE 9th St to SE 10th St, workers are beginning to install the conduits for the new street lighting.