Project Update 1/12/2022

Crews continue to install drainage on SE 9th St between SE 3rd Ave and SE 2nd Ave. Crews are removing trees and landscaping to install drainage system on SE 2nd Ave between SE 10th St and SE 9th St. Sewer removal and replacement continues in Alley 4. Sub grade work is continuing in Alley 5.