Project Update 5/13/2022

Work completed week of 5/9/22

  • SE 9th St, SE 2nd Ave, SE 3rd Ave road reconstruction has begun with subgrade and base rock installed in sections planned for complete reconstruction.
  • On SE 3rd Ave. new sidewalk and driveway aprons are nearing completion between SE 10th St & SE 9th St.

Work scheduled for week of 5/16/22

  • Road reconstruction on SE 9th St between SE 4th Ave & SE 5th St will continue with temporary road closings. Please observe detours and flag men in these areas.
  • Sidewalk and driveway apron replacement will continue on SE 3rd Ave & SE 2nd Ave.
  • Work is ongoing in Alleys 4 and 2.