Project Update 5/13/2022

Work completed week of 5/9/22 SE 9th St, SE 2nd Ave, SE 3rd Ave road reconstruction has begun with subgrade and base rock installed in sections planned for complete reconstruction. On SE 3rd Ave. new sidewalk and driveway aprons are nearing completion between SE 10th St & SE 9th St. Work scheduled for week of… Continue reading

More

Project Update 5/12/2022

Road reconstruction continues on SE 2nd Ave and SE 9th St. New sidewalk and driveway aprons are being backfilled on SE 3rd Ave. Pads for new curb are being constructed on SE 3rd Ave and SE 7th & SE 8th St.

More

Project Update 5/11/2022

Crews are continuing road reconstruction on SE 2nd Ave at SE 8th St and SE 9th St. Concrete crews are removing and replacing driveway aprons on SE 3rd Ave.

More

Project Update 5/10/2022

Road reconstruction continues on SE 2nd Ave between SE 8th St & SE 7th St. Sidewalk removal is ongoing on SE 2nd Ave from SE 7th St to SE 6th St. 12″ Header curb is being installed in Alley 2 between SE 4th Ave & SE 3rd Ave.

More

Project Update 5/9/2022

Driveway aprons are being replaced on SE 3rd Ave. New D curb is being built on SE 9th St. Road work continues on SE 9th St.