Weekly Update 1/6/2023

Work completed this week Final coat of paint applied on bollards in Alley 5 Re-stripe temporary stop bars at all intersections affected by construction Start punch list corrections on drainage structures Week of 1/9/23 Work Schedule Backflow prevention installation on chicanes & bulb outs Continue working on punch list items for project completion

More

Project Update 1/5/2023

The contractor is working on punch list items including finishing painting bollards in Alley 5, repainting temporary stop bars on new asphalt, and improving the concrete on drainage structures and sanitary sewer manholes. The irrigation subcontractor is installing backflow prevention devices in landscaped areas.

More

Project Update 12/21/2022

The contractor continues painting the second coat of safety yellow on the bollards in Alleys 1 & 2.

More

Project Update 12/20/2022

The contractor is painting the bollards in Alley 2.

More

Weekly Update 12/16/2022

Work completed this week Restoration & paving of Alley 4 south of SE 9th St Finish installation of meter boxes in landscaped areas Installation of water meters in landscaped areas Week of 12/19/22 Work Schedule Irrigation and landscaping

More