06 Jan
2023
Weekly Update 1/6/2023
Work completed this week Final coat of paint applied on bollards in Alley 5 Re-stripe temporary stop bars at all intersections affected by construction Start punch list corrections on drainage structures Week of 1/9/23 Work Schedule Backflow prevention installation on chicanes & bulb outs Continue working on punch list items for project completion
05 Jan
2023
Project Update 1/5/2023
The contractor is working on punch list items including finishing painting bollards in Alley 5, repainting temporary stop bars on new asphalt, and improving the concrete on drainage structures and sanitary sewer manholes. The irrigation subcontractor is installing backflow prevention devices in landscaped areas.
22 Dec
2022
Project Update 12/21/2022
The contractor continues painting the second coat of safety yellow on the bollards in Alleys 1 & 2.
20 Dec
2022
16 Dec
2022
Weekly Update 12/16/2022
Work completed this week Restoration & paving of Alley 4 south of SE 9th St Finish installation of meter boxes in landscaped areas Installation of water meters in landscaped areas Week of 12/19/22 Work Schedule Irrigation and landscaping