Project Update 1/15/2021

Work completed this week: SE 4th Ave between SE 5th St to SE 8th St – Crews continued with installing new concrete sidewalks and driveways. SE 4th Ave between SE 9th St to SE 10th St – Crews paved the 1st lift of Asphalt. Alleyway 3 – Crews began framing and pouring the 12” Concrete… Continue reading

More

Project Update 1/14/2021

Crews continue installing sidewalks and driveways and road reconstruction and utility work on SE 4th Avenue between SE 6th and 8th Streets. Crews will start forming and pouring header curb in alleyway 3 starting on the south end at SE 4th Street.

More

Project Update 1/13/2021

Crews continue removing asphalt and backfilling around the new sidewalks and driveways installed on SE 4th Avenue between SE 6th and 7th Streets. Crews will excavate for existing utilities on SE 4th Avenue between SE 7th and 8th Streets and continue with general cleanup along SE 4th Avenue.

More

Project Update 1/12/2021

Crews continue removing and installing sidewalks and driveways on SE 4th Avenue between SE 4th and 5th Streets.

More

Project Update 1/11/2021

Crews continue to install sidewalks and driveways on SE 4th Avenue between SE 6th and 7th Streets. Crews are also installing drainage on SE 3 Avenue and SE 3rd Street.