Project Update 9/18/2020

Work Completed this Week: Installing clean outs in alleyway 3 Clearing and grubbing alleyway 3 in preparation of road crew starting Crews continued to CCTV the existing gravity sewer line to be lined for pre inspection Week of September 21st thru September 25th Work Schedule: Crews will continue replacing the gravity sewer going south in… Continue reading

More

Public Outreach Meeting Notice

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The first one will be held Wednesday, September 30 at 6:00pm. See the below flyer to access the meeting.

More

Project Update 9/17/2020

Crews continue in alleyway 3 installing sewer clean outs.

More

Project Update 9/16/2020

Crews will be in alleyway 3 today installing clean outs on the sewer laterals.

More

Project Update 9/15/2020

Crews are in alleyway 3 to continue clearing and grubbing.

More