Project Update 1/8/2021

Work completed this week: SE 4th Ave between SE 7th St to SE 9th St – Crews continued with installing new concrete sidewalks and driveways. SE 4th Ave between SE 9th St to SE 10th St – Crews installed the new 8” Rock Base and graded for preparation for the 1st lift of asphalt. Alleyway… Continue reading

More

Project Update 1/7/2021

Crews continue road reconstruction on SE 4th Avenue between SE 9th and 10th Streets. Paving this section will be early next week. Crews will also continue installing sidewalks and driveways on SE 4th Avenue between SE 7th and 8th Streets. The removal of sidewalks and driveways will continue on SE 4th Avenue between SE 6th… Continue reading

More

Project Update 1/6/2021

Crews continue installing sidewalks and driveways on SE 4th Avenue between SE 7 and 8th Streets. Road reconstruction continues on SE 4th Avenue between SE 9th and 10th Streets. Crews continue removing sidewalks that are damaged and do not meet ADA requirements on SE 4th Avenue and on 3rd Street near the entrance to Alleyway… Continue reading

More

Project Update 1/5/2021

Crews continue installing sidewalks and driveways on SE 4th Avenue between SE 7th and 8th Streets. Road reconstruction will continue between SE 10th and 9th Streets on SE 4th Avenue. Crews will start removing damaged sidewalks along with sections that do not meet ADA requirements to form and replace in the next few days on… Continue reading

More

Project Update 1/4/2021

Today crews will continue installing sidewalks and driveways on SE 4th Avenue between SE 7th and 8th Streets and total road reconstruction on SE 4th Avenue between SE 9th and 10th Streets.

More