Project Update 9/14/2020

The contractor is continuing to replace gravity sewer south down alleyway 6.

More

Project Update 9/11/2020

Work Completed this week: Crossing SE 2nd Street With replacing the gravity sewer Installed temporary asphalt where they crossed SE 2nd Street Clearing and grubbing alleyway 3 Week of September 14th thru September 18th Work Schedule: Crews will continue replacing the gravity sewer going south in alleyway 6 from SE 2nd street Crews will continue… Continue reading

More

Project Update 9/10/2020

Crews are replacing gravity sewer in alleyway 6 going south from SE 2nd Street. They have crossed SE 2nd Street and are now in the alleyway. Please watch for construction traffic pulling out onto the roadway. Crews are cleaning up from the clearing and grubbing in alleyway 3, and a crew will be cleaning the… Continue reading

More

Project Update 9/9/2020

Crews will continue crossing SE 2nd Street today working south down alleyway 6 replacing the existing 8” sanitary sewer.

More

Project Update 9/8/2020

Today crews will be closing SE 2nd Street between SE 4th Avenue and SE 3rd Avenue to replace existing sewer main south down alleyway 6.

More