Project Update 4/9/2021

Work completed this week: SE 2nd Ave between SE 3rd St to SE 4th St – Pavement reconstruction continued, new concrete sidewalks & driveways completed, 1st lift of Asphalt was placed and pavement markings placed for the parking stalls. SE 4th Ave at SE 5th St – Crews completed the sanitary sewer main repair at… Continue reading

More

Project Update 4/8/2021

Work continues along SE 4th Ave between SE 2nd St to SE 4th St with new concrete sidewalks & driveways installation and excavation for the new Rock Base. Crews are also placing the new pavement markings for parking on the newly paved SE 2nd Ave between SE 3rd St to SE 4th St.

More

Project Update 4/7/2021

Crews are paving the 1st lift of Asphalt on SE 2nd Ave between SE 3rd St to SE 4th St. On SE 4th Ave between SE 2nd St to SE 3rd St, crews are installing new sidewalks & driveways, and at SE 4th Ave and SE 5th St, crews are cleaning up after the sewer… Continue reading

More

Project Update 4/6/2021

Crews are preparing SE 2nd Ave between SE 3rd St to SE 4th St for the 1st lift of Asphalt. Crews are also installing sidewalks along SE 4th Ave between SE 2nd St to SE 3rd St. Sewer Repair work continues on SE 4th Ave at SE 5th St.

More

Project Update 4/5/2021

New concrete sidewalk installation and grading of the new rock base continues on SE 2nd Ave between SE 3rd St to SE 4th St. On SE 4th Ave from SE 5th St to SE 6th St, crews are setting up for the sewer main repair. Crews are also working in Alleyway 3 working on the… Continue reading