Project Update 4/1/2021

Work completed this week: SE 2nd Ave between SE 3rd St to SE 4th St – Pavement reconstruction continued with installing new concrete curb & gutters, sidewalks & driveways and excavating and grading the new 8” Rock Base. SE 4th Ave at SE 5th St – Crews setting up the bypass system for the sewer… Continue reading

More

Reminder – Public Outreach Meeting Tonight!

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The next one will be held Wednesday, March 31 at 6:00pm. To call into the meeting, please dial 1-815-516-0257 and enter Conference ID number 513789794#. To join via web browser or smartphone app, please click bit.ly/OsceolaMeeting. See the… Continue reading

More

Project Update 3/31/2021

Crews are installing bollards in Alleyway 3, continuing with the road work on SE 2nd Street, and setting up for the sewer repair on SE 4th Avenue.

More

Project Update 3/30/2021

Work continues along SE 2nd Ave between SE 3rd St to SE 4th St installing new curbs and grading the rock base. At SE 4th Ave from SE 5th Ave to SE 6th Ave, crew are doing preparation work for the sewer main repair.

More

Project Update 3/29/2021

The contractors began set up for sewer work on SE 4th Avenue. Work will range from SE 6th Street north to SE 5th Street. Valley Gutter will be poured on SE 2nd near SE 3rd Street.