Project Update 8/14/2020

The contractor continues tree removal in Alleyway 6.

More

Project Update 8/13/2020

Contractor continues with tree removal in alleyway 6 and setting up staging area for the project which is located on the southwest corner of SE 2nd Street and SE 3rd Avenue. Contractor is preparing to start on the replacement sanitary sewer line from SE 2nd Street south down alleyway 6 to SE 3rd Street in… Continue reading

More

Project Update 8/12/2020

Crews are removing large trees in alleyway 6 today. Next week moving to alleyway 3 just east of Swinton.

More

Project Update 8/11/2020

The contractor is preparing for large tree removal on Wednesday, August 12th in Alleyway 6 and then in Alleyway 3 when Alleyway 6 is completed.

More

Project Update 8/10/2020

The contractor will continue clearing and grubbing in Alleyway 6 today, moving north from SE 4th Street.

More