Project Update 3/5/2021

Work completed this week: SE 4th Ave between SE 2nd St to SE 4th St – Installation of new concrete sidewalks & driveways continued along the East side. SE 4th Ave from SE 5th St to SE 8th St – Crews paved the 1st lift of Asphalt over the new 8” Rock Base. SE 2nd… Continue reading

More

Project Update 3/4/2021

Road crews will be finishing the road rock on the south half of SE 2nd Avenue. The concrete contractor will continue removing and replacing sidewalks and driveways on SE 4th Avenue between SE 2nd and 3rd Streets.

More

Project Update 3/3/2021

Road reconstruction continues on SE 2nd Avenue and on the sidewalks and driveways on SE 4th Avenue between SE 3rd and 4th streets.

More

Project Update 3/2/2021

Road reconstruction continues on SE 2nd Avenue and SE 4th street along with removing and replacing sidewalks and driveways on SE 4th Avenue between SE 3rd and 4th Streets.

More

Project Update 3/1/2021

The contractor continues road reconstruction on SE 2nd Avenue along with paving the first lift of asphalt on SE 4th Avenue from SE 8th Street to SE 6th Street. The concrete construction will resume on SE 4th Avenue between SE 3rd and 4th streets.