Project Update: 8/12/2020

Crews are removing large trees in alleyway 6 today. Next week moving to alleyway 3 just east of Swinton.

More

Project Update 8/11/2020

The contractor is preparing for large tree removal on Wednesday, August 12th in Alleyway 6 and then in Alleyway 3 when Alleyway 6 is completed.

More

Project Update 8/10/2020

The contractor will continue clearing and grubbing in Alleyway 6 today, moving north from SE 4th Street.

More

Project Update 8/7/2020

The Contractor will start clearing and grubbing alleyway 6, from SE 4th Street moving north. Alleyway 6 is between SE 4 Avenue and SE 3rd Avenue from SE 4th Street north to SE 2nd Street.

More

Project Update 8/6/2020

The Contractor continues with exploratory excavation along SE 4th Avenue, marking existing utilities at various intersections.

More