Project Update 04/30/2018

The design of the Osceola Park Neighborhood Project is well underway and recently hit a milestone with delivery of the Preliminary Design Report to City staff. Some highlights of the efforts underway are: The project components required to create the design drawings have been completed, including: The land survey and base map drawings of the… Continue reading

More

Project Update 01/17/2018

City crews will be installing temporary “traffic calming” measures over the next week including: • Two temporary chicanes – alternating curb bump-outs to narrow the driving lanes – on SE 4th Ave between SE 8th St and SE 9th St; • Two temporary speed cushions on SE 3rd Ave between SE 6th St and SE… Continue reading

More

Neighborhood Kick-off Meeting Powerpoint

Thank you to all who attended the Resident Kick-off Meeting on November 16th. If you were unable to attend the meeting and would like to view a .pdf of the presentation, please CLICK HERE to view.

More

Neighborhood Design Kick-off Meeting Scheduled

Please join us for a Neighborhood Design Kick-off Meeting on Thursday, November 16, 2017 from 6 to 7:30pm at the City’s Environmental Services Division Training Room at 434 South Swinton Avenue. City staff and consultants will provide an overview of the project including how residents can provide input.

More

Welcome to the Osceola Park Project Website

Welcome to the Osceola Park Neighborhood Improvements Project Website!  Check back for updates and new information.

More