Project Update 11/20/2020

Work completed this week SE 4th Ave between SE 6th St to SE 7th St – Installing new 18” RCP Exfiltration Trench and Drainage Structures. SE 4th Ave between SE 2nd St to SE 3rd St – Removing & Replacing the 18” Drainage System. Alleyway 3 at SE 3rd Street – existing gravity sewer replacement… Continue reading

More

Project Update 11/19/2020

Today crews continue installing drainage on SE 4th Avenue at SE 5th Street and between SE 2nd and SE 3rd Streets.

More

Public Outreach Meeting Notice – 11/25/2020

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The next one will be held Wednesday, November 25 at 6:00pm. Please note due to the holidays, there will be no December 2020 public meeting. The Monthly Public Outreach Meetings will resume on January 27, 2020. To call… Continue reading

More

Project Update 11/18/2020

Today crews will continue drainage work in the intersection of SE 4th Avenue and 5th Street and start installing drainage on SE 4th Avenue between SE 2nd and SE 3rd Streets. Crews will complete the header curb and begin the rock base for pervious concrete in the north section of alleyway 6.

More

Project Update 11/17/2020

Today crews will be removing forms from header curb in alleyway 6, installing drainage on SE 4th Avenue in the intersection of SE 4th Avenue and 5th Street along with another crew excavating for existing utilities on SE 4th between SE 3rd and SE 2nd Streets.