Project Update 6/17/2022

Work completed this week New sidewalk & driveway apron replacement on SE 3rd Ave. between SE 8th St and SE 7th St. Driveway apron replacement on SE 9th St. Curb for landscape bulb out on SE 9th St. Road reconstruction started on SE 5th St Work to be completed next week Road crew mobilizing to… Continue reading

More

Project Update 6/16/2022

The concrete crew is pouring new sidewalk and driveway aprons on SE 3rd Ave. Crews are adjusting sewer manhole covers on SE 6th St and backfilling new sidewalks, curb, and driveways.

More

Project Update 6/15/2022

The crew is building pads for new curb and landscape on SE 8th St. New sidewalks and driveway aprons are being backfilled on SE 3rd Ave. The concrete crew is building new curb and landscape on SE 9th St.

More

Project Update 6/14/2022

Crews continue to build new sidewalks on SE 3rd Ave & SE 2nd Ave. The contractor is building pads for sidewalks, new curb, and landscape at SE 9th St at SE 5th Ave. Subgrade work for road reconstruction at the intersection of SE 4th Ave and SE 8th St is ongoing.

More

Project Update 6/13/2022

Crews are building new sidewalks and replacing driveway aprons on SE 3rd Ave. between SE 8th St & SE 7th St. Concrete and asphalt removal for new sidewalk has begun on SE 9th St at SE 5th Ave. New sidewalks, curbs, and driveway aprons are being backfilled on SE 3rd Ave.

More