Project Update 10/21/2020

Today crews will be excavating for existing utilities on SE 4th Avenue near SE 10th Street, weather permitting. Crews will also begin the lining of the existing gravity sewer in Alleyway 3 today.

More

Project Update 10/20/2020

Crews are installing the Pervious concrete in alleyway 6 south and the rock in the same alleyway on the north end preparing for Pervious concrete. Crews are also starting the drainage work on SE 4th Avenue and SE 8th Street working north. Expect daily road closures on SE 4th Avenue.

More

Project Update 10/19/2020

Crews continue with grading and prepping the South section of Alleyway 6 for Pervious Concrete. Work scheduled along SE 4th Ave was cancelled today due to the weather.

More

Project Update 10/16/2020

Work completed this week Gravity Sewer Replacement in Alleyway 6 in now complete. Alleyway 6 South Section – Stone Base complete and Concrete Header Curbs installed. Alleyway 6 North Section – Excavation for Subgrade nearing completion. SE 4th Ave between SE 8th St to SE 7th St – Pavement Area for new drainage work pulverized.… Continue reading

More

Project Update 10/15/2020

Crews continue working in Alleyway 6 with pouring the new concrete header curbs in the south section and also excavating for the sub-base on the north section. Crews also continue with clearing along SE 4th Ave between SE 9th St to SE 10th St.

More