Project Update 10/14/2020

Crews continue in Alleyway 6 pouring the new concrete header curbs in the south section of the Alleyway and also excavating for the sub-base on the north section. Along SE 4th Ave between SE 7th St to SE 8th St, crews are getting ready for the new drainage to be installed.

More

Project Update 10/13/2020

Crews will begin forming the curb in alleyway 6 south. Crews will complete the sanitary sewer replacement in alleyway 6 north on the south end by SE 3rd Stree,t and crews will continue cutting down the north end of alleyway 6 north in preparation for the base rock.

More

Project Update 10/12/2020

Road crew will begin roadwork in alleyway 6 north today. Crews will continue clearing and grubbing along SE 4th Avenue between SE 10th Street and SE 8th Street.

More

Project Update 10/9/2020

Work completed this week Replaced 199’ of gravity sewer in alleyway 6 south from SE 2nd Street Completed base rock work for Pervious Concrete installation in alleyway 6 south Crews continued clearing and grubbing on SE 4th Avenue north from SE 10th Street Work scheduled for Week of October 12th thru October 16th Crews will… Continue reading

More

Project Update 10/8/2020

Crews continue placing the new Base Rock in the South Section in Alleyway 6. On the North Section of Alleyway 6, crews continue with replacing the existing Sanitary Sewer with new 8” PVC pipe.