Project Update 3/5/2021

Work completed this week: SE 4th Ave between SE 2nd St to SE 4th St – Installation of new concrete sidewalks & driveways continued along the East side. SE 4th Ave from SE 5th St to SE 8th St – Crews paved the 1st lift of Asphalt over the new 8” Rock Base. SE 2nd… Continue reading

More

Project Update 3/4/2021

Road crews will be finishing the road rock on the south half of SE 2nd Avenue. The concrete contractor will continue removing and replacing sidewalks and driveways on SE 4th Avenue between SE 2nd and 3rd Streets.

More

Project Update 3/3/2021

Road reconstruction continues on SE 2nd Avenue and on the sidewalks and driveways on SE 4th Avenue between SE 3rd and 4th streets.

More

Project Update 3/2/2021

Road reconstruction continues on SE 2nd Avenue and SE 4th street along with removing and replacing sidewalks and driveways on SE 4th Avenue between SE 3rd and 4th Streets.

More

Project Update 3/1/2021

The contractor continues road reconstruction on SE 2nd Avenue along with paving the first lift of asphalt on SE 4th Avenue from SE 8th Street to SE 6th Street. The concrete construction will resume on SE 4th Avenue between SE 3rd and 4th streets.

More

Project Update 2/26/2021

Work completed this week: Alleyway 6 – Crews completed the Sidewalk and Alleyway Apron at SW 4th Street. SE 2nd Ave between SE 3rd St to SE 4th St – Contractor started road reconstruction, including adding new Concrete Curb & Gutters, Sidewalks, and Driveways. Work scheduled for week of March 1st: SE 4th Ave between… Continue reading

More

Project Update 2/25/2021

Road reconstruction continues on SE 2nd Avenue today with the forming and pouring of the new valley gutter on the east side of SE 2nd Avenue from SE 4th Street.

More

Project Update 2/24/2021

The contractor is installing sidewalks and driveways on SE 2nd Avenue and on SE 4th Street between SE 3rd and 4th Avenues near Alleyway 6.

More

Project Update 2/23/2021

The road contractor is continuing road reconstruction on SE 2nd Avenue. The sidewalk and driveway contractors will form and pour sidewalks and driveways on SE 4th Street near Alleyway 3 and 6.

More

Project Update 2/22/2021

The road contractor will start road reconstruction on SE 2nd Avenue and SE 4th Street. The sidewalk and driveway contractor will form and pour the driveways and sidewalks to Alleyway 6 and 3 on SE 4th Street.

More