Project Update 9/18/2020

Work Completed this Week: Installing clean outs in alleyway 3 Clearing and grubbing alleyway 3 in preparation of road crew starting Crews continued to CCTV the existing gravity sewer line to be lined for pre inspection Week of September 21st thru September 25th Work Schedule: Crews will continue replacing the gravity sewer going south in… Continue reading

More

Public Outreach Meeting Notice

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The first one will be held Wednesday, September 30 at 6:00pm. See the below flyer to access the meeting.

More

Project Update 9/17/2020

Crews continue in alleyway 3 installing sewer clean outs.

More

Project Update 9/16/2020

Crews will be in alleyway 3 today installing clean outs on the sewer laterals.

More

Project Update 9/15/2020

Crews are in alleyway 3 to continue clearing and grubbing.

More

Project Update 9/14/2020

The contractor is continuing to replace gravity sewer south down alleyway 6.

More

Project Update 9/11/2020

Work Completed this week: Crossing SE 2nd Street With replacing the gravity sewer Installed temporary asphalt where they crossed SE 2nd Street Clearing and grubbing alleyway 3 Week of September 14th thru September 18th Work Schedule: Crews will continue replacing the gravity sewer going south in alleyway 6 from SE 2nd street Crews will continue… Continue reading

More

Project Update 9/10/2020

Crews are replacing gravity sewer in alleyway 6 going south from SE 2nd Street. They have crossed SE 2nd Street and are now in the alleyway. Please watch for construction traffic pulling out onto the roadway. Crews are cleaning up from the clearing and grubbing in alleyway 3, and a crew will be cleaning the… Continue reading

More

Project Update 9/9/2020

Crews will continue crossing SE 2nd Street today working south down alleyway 6 replacing the existing 8” sanitary sewer.

More

Project Update 9/8/2020

Today crews will be closing SE 2nd Street between SE 4th Avenue and SE 3rd Avenue to replace existing sewer main south down alleyway 6.

More