30 Jun
2023
Weekly Update 6/30/2023
Work completed this week Final lift of asphalt SE 3rd Ave at SE 5th St. Mill & Pave intersection of SE 4th Ave & SE 5th St. Mill & Pave Se 4th Ave north of SE 6th St to correct damage caused during sewer bypass operations. Pave small area in parking lot of Currie Common… Continue reading
20 Jun
2023
Project Update 6/20/2023
The contractor has been trimming the new sod in swales and right of ways and performing general cleanup of the site.
16 Jun
2023
Weekly Update 6/16/2023
Work completed this week Curb and ADA ramp removal & replacement on SE 3rd Ave at SE 5th St Removal of concrete, dirt, and rocks from staging area Removal and replacement of damaged sidewalk surrounding staging area Week of 6/19/23 Speed humps installation on SE 2nd Ave and SE 3rd Ave Permanent striping on roadways… Continue reading
15 Jun
2023
Project Update 6/15/2023
The contractor is installing conduits for power to the irrigation on SE 5th St. Curb and sidewalks are being completed on SE 3rd Ave at SE 5th St.
14 Jun
2023
Project Update 6/14/2023
The contractor is conducting inspections of manhole coatings, and working on irrigation on SE 5th St.
13 Jun
2023
Project Update 6/13/2023
The contractor is removing concrete from the project area. Curb is being replaced on SE 3rd Ave. and SE 5th St, and sidewalks are being replaced on SW 2nd St and SW 6th Ave.
12 Jun
2023
Project Update 6/12/2023
The contractor is removing sidewalk and curb to be replaced on SE 3rd Ave at SE 5th St. Sidewalk is being replaced in the areas around the staging area on SE 2nd St and SE 6th Ave.
09 Jun
2023
Weekly Update 6/9/2023
Work completed this week 95% completion of final asphalt on roadways. Temporary stop bars and crosswalks at intersections. Finish grading of contractor staging area on SW 2nd St and SW 6th Ave. Removal of sidewalk to be replaced on SW 2nd Ave at staging area. Week of 6/12/23 Adjustment of curbs on SE 3rd Ave… Continue reading
07 Jun
2023
Project Update 6/7/2023
New asphalt is being installed on SE 3rd Ave. between SE 8th St & SE 4th St. Please drive carefully through the construction zone and obey flaggers, temporary road closures, and detours.
06 Jun
2023
Project Update 6/6/2023
The final lift of new asphalt is being installed on SE 2nd Ave, SE 3rd Ave, and parking areas at Currie Common Park on SE 7th & SE 8th St. Please drive carefully through the construction zone and obey flaggers and detours.