Project Update 11/22/2022

The contractor is preparing all of the areas to be landscaped on SE 5th St, SE 7th St, and SE 8th St. New Sabal palmetto trees have been planted on SE 5th St.

More

Weekly Update 11/18/2022

Work completed this week: Remove shrubbery, rocks and roots from islands on S.E. 5th St. Place planting soil in preparation for sabal palmetto trees. Begin tree installation on SE 5th St islands. Week of 11/21/22 Work Schedule: Place planting soil on chicanes & bulbouts. Residential irrigation repair. Topsoil and sod installation.  

More

Project Update 11/17/2022

The islands on SE 5th St are being prepared for trees and shrubbery to be planted.

More

Project Update 11/16/2022

The landscape contractor is working to remove existing shrubbery in the islands on SE 5th St.

More

Weekly Update 11/11/2022

Work completed this week Remove equipment from staging area United Fiber Optics installed decorative lighting on SE 7th St at Currie Common Park Painted curbing on SE 7th St & SE 8th St Irrigation subcontractor completing irrigation on SE 5th St islands Contractor secured job site and staging area for Hurricane Nicole on 11/8 and… Continue reading

More

Project Update 11/9/2022

The contractor is cleaning up the storage area onsite and removing equipment that is no longer needed. The irrigation contractor is working on SE 5th Street between SE 4th and SE 5th Avenues. The jobsite has been secured for the approaching storm, and the contractor will be back onsite after the storm.

More

Project Update 11/7/2022

The contractor has begun demobilizing equipment from the staging area. Landscape work is set to begin in chicanes and bulbouts with sod to be delivered and installed.

More

Weekly Update 11/4/2022

Work completed this week Bollard installation in Alley 2 except for the signage on the additional Bollards.  Painting of the newly constructed D- curb. Coating of the sanitary sewer manholes. Root pruning and grading of the median on SE 5th Street. Week of 11/7/22 Work Schedule Residential irrigation restoration. Begin landscaping of chicanes & bulb… Continue reading

More

Project Update 11/3/2022

The contractor is installing the signage on the bollards in Alley 2, root pruning the trees, grading the median on SE 5th Street, and painting the newly installed curbing on the project.

More

Project Update 11/1/2022

The contractor continues working on the storm drainage system on SE 3rd Avenue and SE 8th and 9th Streets. The irrigation contractor continues installing irrigation on SE 5th Street and SE 4th Avenue.

More