Project Update 11/30/2020

Today crews will be installing Pervious concrete in alleyway 6 north section and installing the liner in the south section of alleyway 6 sanitary sewer. Also crews will be working on SE 4th Avenue to prepare for a deflection in the existing water main and to switch over 5 water services to new water service… Continue reading

More

Public Outreach Meeting Tonight!

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The next one will be held tonight, November 25 at 6:00pm. Please note due to the holidays, there will be no December 2020 public meeting. The Monthly Public Outreach Meetings will resume on January 27, 2020. To call… Continue reading

More

Project Update 11/25/2020

Work completed this week SE 4th Ave between SE 2nd St to SE 8th St – crews installed new drainage pipe and drainage structures. Alleyway 6 North Section – Rock Base installed and placement of the Pervious Concrete began. No work is scheduled November 26 in observance of Thanksgiving holiday. Work scheduled for Friday &… Continue reading

More

Project Update 11/24/2020

Today crews will continue installing drainage on SE 4th Avenue and SE 2nd Street and remove the old drainage structure. On SE 4th between SE 10th Street and SE 5th Street crews will be excavating for existing utilities to start road reconstruction early next month.

More

Project Update 11/23/2020

Today crews will continue installing drainage on SE 4th Avenue between SE 2nd Street and SE 3rd Street. SE 4th Avenue will be closed from SE 4th Street thru SE 2nd Street today along with SE 3rd Street.

More

Project Update 11/20/2020

Work completed this week SE 4th Ave between SE 6th St to SE 7th St – Installing new 18” RCP Exfiltration Trench and Drainage Structures. SE 4th Ave between SE 2nd St to SE 3rd St – Removing & Replacing the 18” Drainage System. Alleyway 3 at SE 3rd Street – existing gravity sewer replacement… Continue reading

More

Project Update 11/19/2020

Today crews continue installing drainage on SE 4th Avenue at SE 5th Street and between SE 2nd and SE 3rd Streets.

More

Public Outreach Meeting Notice – 11/25/2020

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The next one will be held Wednesday, November 25 at 6:00pm. Please note due to the holidays, there will be no December 2020 public meeting. The Monthly Public Outreach Meetings will resume on January 27, 2020. To call… Continue reading

More

Project Update 11/18/2020

Today crews will continue drainage work in the intersection of SE 4th Avenue and 5th Street and start installing drainage on SE 4th Avenue between SE 2nd and SE 3rd Streets. Crews will complete the header curb and begin the rock base for pervious concrete in the north section of alleyway 6.

More

Project Update 11/17/2020

Today crews will be removing forms from header curb in alleyway 6, installing drainage on SE 4th Avenue in the intersection of SE 4th Avenue and 5th Street along with another crew excavating for existing utilities on SE 4th between SE 3rd and SE 2nd Streets.

More