Project Update 1/19/2022

Crews are installing the drainage system on SE 9th St at SE 3rd Ave. and removing asphalt on SE 6th St to prepare for the next drainage installation. Sewer replacement continues in Alley 2. Alley 5 sub grade between SE 9th St & SE 10th St has been inspected and is ready for base rock.

More

Project Update 1/18/2022

Crews are installing drainage on SE 9th St. and SE 6th St at SE 4th Ave. Crews are also performing sewer replacement in Alley 2 between SE 3rd Ave. and SE 4th Ave. and are finishing clearing and grubbing and sub grade preparation in Alley 5.

More

Project Update 1/17/2022

Crews continue to install drainage on SE 9th St. Crews are preparing the new water line on SE 9th St for chlorination. Alley 2 sewers are being removed and replaced, and Alley 5 sub grade is being prepared for inspection. Clearing and grubbing is underway on SE 6th St.

More

Weekly Update 1/14/2022

Work Completed this Week Alleyway 4 between SE 8th St to SE 10th St – Sanitary Sewer Replacement Installation. SE 9th St between SE 3rd Ave and SE 2th Ave – Storm Drainage Installation. SE 2nd Ave Storm Drainage System Installation. Tie in approved new water line SE 8th St at SE 5th Ave. Week… Continue reading

More

Project Update 1/14/2022

Crews are continuing to install new drainage on SE 9th St. Sewer removal and replacement has begun in Alley 2 between SE 4th Ave & SE 3rd Ave. The new 8″ water line has been connected to the existing system on SE 8th St at SE 5th Ave.

More

Project Update 1/13/2022

Contractor is continuing to install new drainage system on SE 9th St. Crews are finishing new drainage system on SE 2nd Ave. Alley 4 is being graded and restored, and Alley 5 sub grade work is ongoing.

More

Project Update 1/12/2022

Crews continue to install drainage on SE 9th St between SE 3rd Ave and SE 2nd Ave. Crews are removing trees and landscaping to install drainage system on SE 2nd Ave between SE 10th St and SE 9th St. Sewer removal and replacement continues in Alley 4. Sub grade work is continuing in Alley 5.

More

Project Update 1/11/2022

Crews continue to install drainage on Se 8th St. Crews are removing and replacing sewer in Alley 4 south of SE 9th St. Crews are also removing asphalt at intersection of SE 9th St & SE 3rd Ave to prepare for installation of the next drainage section.

More

Project Update 1/10/2022

Crews are installing storm drain systems SE 8th St at SE 3rd Ave and at SE 8th St at SE 3rd Ave. Crews are also removing and replacing sewer main in Alley 4 crossing SE 9th St. Alley 5 is being prepared for subgrade and curb installation.

More

Project Update 1/7/2022

Crews continue drainage installation. Crews also are working at SE 8th St and SE 9th Streets at 3rd Ave installing new structures and pipe. Work in Alley 4 between SE 8th St and SE 9th St continues replacing sanitary sewer main and laterals.

More