Weekly Update 3/31/2023

Work completed this week Restoration of areas behind curb in Alley 2, and Alley 5 disturbed by construction Removal of defective/damaged pervious concrete in Alleys 5, 2, and 1 ​Week of 4/3/23 Replace concrete curb, sidewalk, and defective pervious concrete Restoration of areas behind curb in alleys Topsoil and sod replacement and installation

More

Project Update 3/30/2023

The contractor is removing pervious concrete in Alley 5 and Alley 2 in preparation for replacement next week.

More

Project Update 3/29/2023

The contractor is removing concrete in Alley 5 which will be replaced next week.

More

Project Update 3/28/2023

The contractor is preparing Alleys 2 and 5 for restoration.

More

Project Update 3/27/2023

Crews are performing restoration work behind the curb in Alley 2 between SE 4th Ave and 3rd Ave.  

More

Weekly Update 3/24/2023

Work completed this week Restoration of areas behind curb in alley 2 disturbed by construction Residential mailboxes returned to their original locations. Week of 3/27/23  Concrete curb, sidewalk & defective pervious concrete to be replaced. Restoration of areas behind curb in alleys. Topsoil and sod replacement and installation.

More

Project Update 3/23/2023

Several subcontractors are on site repairing curbs in the alleys, adjusting chicanes on SE 3rd Ave and SE 2nd Ave, and adjusting the height of decorative light poles.

More

Project Update 3/22/2023

The contractor is installing mailboxes at original locations.

More

Project Update 3/21/2023

The contractor is working on the placement of the perforated stainless-steel catch basin covers.

More

Weekly Update 3/17/2023

Work completed this week Restoration of areas behind sidewalk disturbed by construction Punch list corrections to road on SE 5th S Week of 3/20/23  Continue to address punch list items Restoration of areas behind curb in alleys

More