Project Update 6/24/2022

Work completed this week: New sidewalks and driveway apron replacement on SE 6th St., SE 7th St. & SE 3rd Ave. New header curb for bulb outs on SE 9th St. & SE 8th St. at SE 5th Ave. Road reconstruction on SE 6th St. at SE 4th Ave. & SE 5th St. east of… Continue reading

More

Project Update 6/23/2022

New sidewalks and driveway aprons are being constructed on SE 7th St. and SE 6th St. Crews are removing existing sidewalk for replacement on SE 3rd Ave. north of SE 7th St. Road reconstruction continues on SE 5th St. between SE 5th Ave. and SE 4th Ave. Please observe detour signage and use caution in… Continue reading

More

Project Update 6/22/2022

New sidewalks and driveway aprons are being built on SE 3rd Ave., SE 6th St. and SE 7th St. Road reconstruction is underway on SE 6th St. and SE 5th St. Occasional temporary road closures are possible. Please observe detour signage and use caution in the work zone.

More

Project Update 6/21/2022

Crews are continuing with road reconstruction on SE 3rd Ave., south of SE 4th St. New sidewalks and curbs are being built on SE 6th St. and SE 3rd Ave. Driveway aprons are being removed for replacement on SE 7th St. Roads may be closed in these areas, please obey detour signage.

More

Project Update 6/20/2022

Sidewalk pads are being built on SE 9th St. Drainage structure frames are being adjusted to proper elevations on SE 3rd Ave. Road reconstruction is beginning on SE 3rd Ave.

More

Project Update 6/17/2022

Work completed this week New sidewalk & driveway apron replacement on SE 3rd Ave. between SE 8th St and SE 7th St. Driveway apron replacement on SE 9th St. Curb for landscape bulb out on SE 9th St. Road reconstruction started on SE 5th St Work to be completed next week Road crew mobilizing to… Continue reading

More

Project Update 6/16/2022

The concrete crew is pouring new sidewalk and driveway aprons on SE 3rd Ave. Crews are adjusting sewer manhole covers on SE 6th St and backfilling new sidewalks, curb, and driveways.

More

Project Update 6/15/2022

The crew is building pads for new curb and landscape on SE 8th St. New sidewalks and driveway aprons are being backfilled on SE 3rd Ave. The concrete crew is building new curb and landscape on SE 9th St.

More

Project Update 6/14/2022

Crews continue to build new sidewalks on SE 3rd Ave & SE 2nd Ave. The contractor is building pads for sidewalks, new curb, and landscape at SE 9th St at SE 5th Ave. Subgrade work for road reconstruction at the intersection of SE 4th Ave and SE 8th St is ongoing.

More

Project Update 6/13/2022

Crews are building new sidewalks and replacing driveway aprons on SE 3rd Ave. between SE 8th St & SE 7th St. Concrete and asphalt removal for new sidewalk has begun on SE 9th St at SE 5th Ave. New sidewalks, curbs, and driveway aprons are being backfilled on SE 3rd Ave.

More