31 Mar
2023
Weekly Update 3/31/2023
Work completed this week Restoration of areas behind curb in Alley 2, and Alley 5 disturbed by construction Removal of defective/damaged pervious concrete in Alleys 5, 2, and 1 Week of 4/3/23 Replace concrete curb, sidewalk, and defective pervious concrete Restoration of areas behind curb in alleys Topsoil and sod replacement and installation
30 Mar
2023
Project Update 3/30/2023
The contractor is removing pervious concrete in Alley 5 and Alley 2 in preparation for replacement next week.
29 Mar
2023
Project Update 3/29/2023
The contractor is removing concrete in Alley 5 which will be replaced next week.
28 Mar
2023
27 Mar
2023
Project Update 3/27/2023
Crews are performing restoration work behind the curb in Alley 2 between SE 4th Ave and 3rd Ave.
24 Mar
2023
Weekly Update 3/24/2023
Work completed this week Restoration of areas behind curb in alley 2 disturbed by construction Residential mailboxes returned to their original locations. Week of 3/27/23 Concrete curb, sidewalk & defective pervious concrete to be replaced. Restoration of areas behind curb in alleys. Topsoil and sod replacement and installation.
23 Mar
2023
Project Update 3/23/2023
Several subcontractors are on site repairing curbs in the alleys, adjusting chicanes on SE 3rd Ave and SE 2nd Ave, and adjusting the height of decorative light poles.
22 Mar
2023
21 Mar
2023
Project Update 3/21/2023
The contractor is working on the placement of the perforated stainless-steel catch basin covers.
17 Mar
2023
Weekly Update 3/17/2023
Work completed this week Restoration of areas behind sidewalk disturbed by construction Punch list corrections to road on SE 5th S Week of 3/20/23 Continue to address punch list items Restoration of areas behind curb in alleys