Project Update 9/3/2020

The Contractor is installing clean outs in alleyway 3 today along with some light clearing and grubbing.

More

Project Update 9/2/2020

Crews are installing clean outs in alleyway 6.

More

Project Update 9/1/2020

Crews will continue clearing alleyway 3 and installing clean outs in alleyway 6 today.

More

Project Update 8/31/2020

The contractor continued with clearing alleyway 3 with the removal of a large Mahogany tree and began installing clean outs on the sewer laterals in alleyway 6.

More

Project Update 8/28/2020

Crews continue clearing and grubbing in alleyway 3.

More

Project Update 8/27/2020

Crews continue clearing and grubbing in alleyway 3.

More

Project Update 8/26/2020

Crews continue clearing and grubbing in alleyway 3.

More

Project Update 8/25/2020

Crews continue clearing and grubbing in alleyway 3.

More

Project Update 8/24/2020

The contractor is clearing and grubbing in alleyway 3.

More

Project Update 8/24/2020

Work Completed Last Week Clearing and grubbing in alleyway 6 Start clearing and grubbing in alleyway 3 Clean up in preparation for the approaching storm FPL has relocated some of their poles that were in conflict with the project Set up staging area Work Scheduled for this Week Continue clearing and grubbing in alleyway 3… Continue reading