Project Update 10/12/2020

Road crew will begin roadwork in alleyway 6 north today. Crews will continue clearing and grubbing along SE 4th Avenue between SE 10th Street and SE 8th Street.

More

Project Update 10/9/2020

Work completed this week Replaced 199’ of gravity sewer in alleyway 6 south from SE 2nd Street Completed base rock work for Pervious Concrete installation in alleyway 6 south Crews continued clearing and grubbing on SE 4th Avenue north from SE 10th Street Work scheduled for Week of October 12th thru October 16th Crews will… Continue reading

More

Project Update 10/8/2020

Crews continue placing the new Base Rock in the South Section in Alleyway 6. On the North Section of Alleyway 6, crews continue with replacing the existing Sanitary Sewer with new 8” PVC pipe.

More

Project Update 10/7/2020

Crews will continue replacing the existing gravity sewer pipe in alleyway 6 north and clearing and grubbing on SE 4th Avenue north from SE 10th Street.

More

Project Update 10/6/2020

Crews continue to replace the existing gravity sewer in alleyway 6 north. In alleyway 6 south, they are installing the rock base for the pervious concrete. The crew on SE 4th Avenue is clearing and grubbing on the west side of the road.

More

Project Update 10/6/2020

Crews continue to replace the existing gravity sewer in alleyway 6 north. In alleyway 6 south, they are installing the rock base for the pervious concrete. The crew on SE 4th Avenue is clearing and grubbing on the west side of the road.

More

Project Update 10/6/2020

Crews continue to replace the existing gravity sewer in alleyway 6 north. In alleyway 6 south, they are installing the rock base for the pervious concrete. The crew on SE 4th Avenue is clearing and grubbing on the west side of the road.

More

Project Update 10/05/2020

Today, crews are continuing with the replacement of the existing gravity sewer in alleyway 6 north and the road work in alleyway 6 south. There is also one crew clearing and grubbing on SE 4th Avenue working north on the west side of SE 4th Avenue.

More

Project Update 10/2/2020

Due to today’s weather, crews will work together on the south section of alleyway 6 to prepare for subgrade inspection and hand work around manholes. Work completed this week on NE 4th and Beach Drive Replaced 110’ of gravity sewer in alleyway 6 south from SE 2nd Street Completed subgrade work for Pervious Concrete installation… Continue reading

More

Project Update 10/1/2020

The contractor will continue replacing the existing gravity sewer system in alleyway 6 and clearing and grubbing on SE 4th Avenue north from SE 10th Street.

More