Project Update 1/26/2021

Crews continue installing sidewalks, driveways and roadway reconstruction on SE 4th Avenue between SE 5th and SE 7th Streets.

More

Public Outreach Meeting Notice – 1/27/2021

The City will be holding monthly public outreach meetings online to inform residents of the project’s progress. The next one will be held Wednesday, January 27 at 6:00pm. To call into the meeting, please dial 1-815-516-0257 and enter Conference ID number 513789794#. To join via web browser or smartphone app, please click bit.ly/OsceolaMeeting See the… Continue reading

More

Project Update 1/25/2021

Crews continue sidewalk and driveway installation along with road reconstruction and preparation for a sanitary sewer point repair on SE 4th Avenue between SE 5th and 7th Streets.

More

Project Update 1/22/2021

Work completed this week: SE 4th Ave between SE 5th St to SE 7th Ave – Crews continued with installing new concrete sidewalks and driveways and constructing new Rock Base. Alleyway 3 – Concrete Header Curbs were completed. SE 4th Ave at SE 5th St – Crews began setting up the dewatering system for the… Continue reading

More

Project Update 1/21/2021

Crews continue roadway reconstruction on SE 4th Avenue between SE 6th and 7th streets. They also continue with the preparation work for the point repair on the existing gravity sewer at the intersection of SE 4th Avenue and SE 5th Street.

More

Project Update 1/20/2021

Crews continue installing sidewalks and driveways on SE 4th Avenue between SE 6th and SE 7th Streets. Crews continue work in alleyway 3 in preparation for the new Pervious concrete.

More

Project Update 1/19/2021

Crews continue roadway reconstruction and installing sidewalks and driveways on SE 4th Avenue between SE 6th and SE 7th streets. The concrete crews are back in Alleyway 3 installing header curb on the east side working north to south from SE 3rd Street.

More

Project Update 1/18/2021

Crews continue roadway reconstruction and prepare for a point repair on the sewer main on SE 4th Avenue between SE 5th and SE 7th streets. The concrete crews are back in Alleyway 3 installing header curb on the east side working north to south from SE 3rd Street.

More

Project Update 1/15/2021

Work completed this week: SE 4th Ave between SE 5th St to SE 8th St – Crews continued with installing new concrete sidewalks and driveways. SE 4th Ave between SE 9th St to SE 10th St – Crews paved the 1st lift of Asphalt. Alleyway 3 – Crews began framing and pouring the 12” Concrete… Continue reading

More

Project Update 1/14/2021

Crews continue installing sidewalks and driveways and road reconstruction and utility work on SE 4th Avenue between SE 6th and 8th Streets. Crews will start forming and pouring header curb in alleyway 3 starting on the south end at SE 4th Street.

More